Here we would like to draw your attention to COGI transaction code in SAP. As we know it is being used in the SAP PP-SFC (Production Orders – PP) component which is coming under PP module (Production Planning).COGI is a transaction code used for Postprocess Faulty Goods Movements in SAP.
It comes under the package CORU.When we execute this transaction code, CORUAFFW is the normal standard SAP program that is being executed in background.
SAP COGI menu path
See the possible menu paths to access the same report by avoiding entering the transaction code.
Path 1
Logistics → Production → Repetitive Manufacturing → Backflush → Postprocess → Postprocessing Individual Components
Path 2
Logistics → Production → KANBAN → Environment → Repetitive Manufacturing → Backflush → Postprocess → Postprocessing Individual Components
Path 3
Logistics → Project System → Progress → Confirmation → Reprocessing → Reprocess Goods Issue Postings with Erro
Path 4
Accounting → Project System → Progress → Confirmation → Reprocessing → Reprocess Goods Issue Postings with Erro
Path 5
Logistics → Production – Process → Process Order → Environment → Material Movement → Failed Goods Movements
Path 6
Logistics → Production – Process → Process Planning → Requirements → Process order → Environment → Material Movement → Failed Goods Movements
Path 7
Logistics → Production – Process → Process Planning → Environment → Process management → Environment → Process Orders → Environment → Material Movement → Failed Goods Movements
Path 8
Logistics → Production – Process → Process Management → Environment → Process Orders → Environment → Material Movement → Failed Goods Movements
Path 9
Logistics → Production – Process → Process Management → Environment → Process Planning → Requirements → Process order → Environment → Material Movement → Failed Goods Movements
Path 10
Logistics → Sales and Distribution → Sales → Product Cost by Sales Order → Actual Postings → Time Sheet → Transfer → Plant Maintenance/Customer Service → Postprocessing Goods Movements
Path 11
Logistics → Sales and Distribution → Sales → Product Cost by Sales Order → Actual Postings → Time Sheet → Transfer → Project System → Postprocessing Goods Movements
Path 12
Logistics → Production → Shop Floor Control → Confirmation → Reprocessing → Goods Movements
Path 13
Logistics → Production → Capacity Planning → Requirements → Production Order → Confirmation → Reprocessing → Goods Movements
Path 14
Logistics → Production → Capacity Planning → Requirements → Maintenance Order → Completion Confirmation → Postprocessing → Goods Issues
Path 15
Logistics → Production → KANBAN → Environment → Production Orders → Confirmation → Reprocessing → Goods Movements
Path 16
Logistics → Plant Maintenance → Maintenance Processing → Completion Confirmation → Entry → Time Sheet → Transfer → Plant Maintenance/Customer Service → Postprocessing Goods Movements
Path 17
Logistics → Plant Maintenance → Maintenance Processing → Completion Confirmation → Entry → Time Sheet → Transfer → Project System → Postprocessing Goods Movements
Path 18
Logistics → Plant Maintenance → Maintenance Processing → Completion Confirmation → Postprocessing → Goods Issues
Path 19
Logistics → Customer Service → Service Processing → Confirmation → Entry → Time Sheet → Transfer → Plant Maintenance/Customer Service → Postprocessing Goods Movements
Path 20
Logistics → Customer Service → Service Processing → Confirmation → Entry → Time Sheet → Transfer → Project System → Postprocessing Goods Movements
Path 21
Logistics → Customer Service → Service Processing → Confirmation → Postprocessing → Goods Issues
Path 22
Logistics → Project System → Progress → Confirmation → Time Sheet → Transfer → Plant Maintenance/Customer Service → Postprocessing Goods Movements
Path 23
Logistics → Project System → Progress → Confirmation → Time Sheet → Transfer → Project System → Postprocessing Goods Movements
Path 24
Logistics → Project System → Resources → Capacity Requirements Planning → Requirements → Production Order → Confirmation → Reprocessing → Goods Movements
Path 25
Logistics → Project System → Resources → Capacity Requirements Planning → Requirements → Maintenance Order → Completion Confirmation → Postprocessing → Goods Issues
Path 26
Accounting → Controlling → Cost Center Accounting → Actual Postings → Time sheet → Transfer → Plant Maintenance/Customer Service → Postprocessing Goods Movements
Path 27
Accounting → Controlling → Cost Center Accounting → Actual Postings → Time sheet → Transfer → Project System → Postprocessing Goods Movements
Path 28
Accounting → Controlling → Internal Orders → Actual Postings → Time Sheet → Transfer → Plant Maintenance/Customer Service → Postprocessing Goods Movements
Path 29
Accounting → Controlling → Internal Orders → Actual Postings → Time Sheet → Transfer → Project System → Postprocessing Goods Movements
Path 30
Accounting → Controlling → Activity-Based Costing → Actual Postings → Time Sheet → Transfer → Plant Maintenance/Customer Service → Postprocessing Goods Movements
Path 31
Accounting → Controlling → Activity-Based Costing → Actual Postings → Time Sheet → Transfer → Project System → Postprocessing Goods Movements
Path 32
Accounting → Investment Management → Internal Orders → Actual Postings → Time Sheet → Transfer → Plant Maintenance/Customer Service → Postprocessing Goods Movements
Path 33
Accounting → Investment Management → Internal Orders → Actual Postings → Time Sheet → Transfer → Project System → Postprocessing Goods Movements
Path 34
Accounting → Investment Management → Investment Projects → Actual Postings → Time Sheet → Transfer → Plant Maintenance/Customer Service → Postprocessing Goods Movements
Path 35
Accounting → Investment Management → Investment Projects → Actual Postings → Time Sheet → Transfer → Project System → Postprocessing Goods Movements
Path 36
Accounting → Project System → Progress → Confirmation → Time Sheet → Transfer → Plant Maintenance/Customer Service → Postprocessing Goods Movements
Path 37
Accounting → Project System → Progress → Confirmation → Time Sheet → Transfer → Project System → Postprocessing Goods Movements
Path 38
Accounting → Project System → Resources → Capacity Requirements Planning → Requirements → Production Order → Confirmation → Reprocessing → Goods Movements
Path 39
Accounting → Project System → Resources → Capacity Requirements Planning → Requirements → Maintenance Order → Completion Confirmation → Postprocessing → Goods Issues
Path 40
Human Resources → Time Management → Time Sheet → Transfer → Plant Maintenance/Customer Service → Postprocessing Goods Movements
Path 41
Human Resources → Time Management → Time Sheet → Transfer → Project System → Postprocessing Goods Movements
Transaction COGI technical data table
Tcode | COGI |
Purpose | Postprocess Faulty Goods Movements |
Module | PP |
Component | PP-SFC |
SAP Package | CORU |
Program running | CORUAFFW |
Object | C_AFFW_TWK |
Screen No | 1000 |
Type | R |
Some Basic Questions & Answers
Program named CORUAFFW will run when we enter transaction code COGI.
COGI is a Report Transaction code type which is shortly represented as R.