Here we would like to draw your attention to CM53 transaction code in SAP. As we know it is being used in the SAP PP-CRP (Capacity Requirements Planning – PP) component which is coming under PP module (Production Planning).CM53 is a transaction code used for Capacity leveling: PS elem/version in SAP.
It comes under the package CY01.
SAP CM53 menu path
See the possible menu paths to access the same report by avoiding entering the transaction code.
Path 1
Logistics → Production → Shop Floor Control → Information System → Capacity Evaluation → Extended Evaluation → Project View → WBS Element/Version
Path 2
Logistics → Production → Capacity Planning → Evaluation → Extended Evaluation → Project View → WBS Element/Version
Path 3
Logistics → Plant Maintenance → Maintenance Processing → Capacity Requirements Planning → Leveling → General → Evaluation → Extended Evaluation → Project View → WBS Element/Version
Path 4
Logistics → Customer Service → Service Processing → Order → Capacity Planning → Leveling → General → Evaluation → Extended Evaluation → Project View → WBS Element/Version
Path 5
Logistics → Project System → Resources → Capacity Requirements Planning → Evaluation → Extended Evaluation → Project View → WBS Element/Version
Path 6
Accounting → Project System → Resources → Capacity Requirements Planning → Evaluation → Extended Evaluation → Project View → WBS Element/Version
Path 7
Information Systems → General Report Selection → Production Planning → Capacity Requirements Planning → Capacity leveling: PS elem/version
Path 8
Information Systems → General Report Selection → Production Planning → Production Control → Capacity Evaluation → Extended Evaluation → Project View → WBS Element/Version
Path 9
Logistics → Project System → Project → Simulation → Capacity Load Utilization → Project
Transaction CM53 technical data table
Tcode | CM53 |
Purpose | Capacity leveling: PS elem/version |
Module | PP |
Component | PP-CRP |
SAP Package | CY01 |
Type | P |