Here we would like to draw your attention to CM03 transaction code in SAP. As we know it is being used in the SAP PP-CRP (Capacity Requirements Planning – PP) component which is coming under PP module (Production Planning).CM03 is a transaction code used for Capac. planning, work center pool in SAP.
It comes under the package CY.When we execute this transaction code, SAPMC65A is the normal standard SAP program that is being executed in background.
SAP CM03 menu path
See the possible menu paths to access the same report by avoiding entering the transaction code.
Path 1
Logistics → Production → Shop Floor Control → Information System → Capacity Evaluation → Work Center View → Released Orders
Path 2
Information Systems → General Report Selection → Production Planning → Production Control → Capacity Evaluation → Work Center View → Released Orders
Path 3
Logistics → Production → Capacity Planning → Evaluation → Work Center View → Pool
Path 4
Logistics → Production → Capacity Planning → Requirements → Maintenance Order → Capacity Requirements Planning → Evaluation → Work Center View → Pool
Path 5
Logistics → Production – Process → Process Order → Environment → Process Planning → Evaluation → Resource view → Pool
Path 6
Logistics → Production – Process → Process Planning → Evaluation → Resource view → Pool
Path 7
Logistics → Production – Process → Process Management → Environment → Process Planning → Evaluation → Resource view → Pool
Path 8
Logistics → Plant Maintenance → Maintenance Processing → Capacity Requirements Planning → Evaluation → Work Center View → Pool
Path 9
Logistics → Plant Maintenance → Maintenance Processing → Capacity Requirements Planning → Leveling → General → Evaluation → Work Center View → Pool
Path 10
Logistics → Customer Service → Service Processing → Order → Capacity Planning → Leveling → General → Evaluation → Work Center View → Pool
Path 11
Logistics → Project System → Resources → Capacity Requirements Planning → Evaluation → Work Center View → Pool
Path 12
Logistics → Project System → Resources → Capacity Requirements Planning → Requirements → Maintenance Order → Capacity Requirements Planning → Evaluation → Work Center View → Pool
Path 13
Logistics → Customer Service → Service Processing → Order → Capacity Planning → Evaluation → Queue
Path 14
Information Systems → General Report Selection → Production Planning → Capacity Requirements Planning → Capacity Planning, Work Center Pool
Transaction CM03 technical data table
Tcode | CM03 |
Purpose | Capac. planning, work center pool |
Module | PP |
Component | PP-CRP |
SAP Package | CY |
Program running | SAPMC65A |
Screen No | 1 |
Type | P |
Some Basic Questions & Answers
Program named SAPMC65A will run when we enter transaction code CM03.
CM03 is a Parameter Transation code type which is shortly represented as P.