CM02 SAP tcode for – Capac. planning, work center orders

Here we would like to draw your attention to CM02 transaction code in SAP. As we know it is being used in the SAP PP-CRP (Capacity Requirements Planning – PP) component which is coming under PP module (Production Planning).CM02 is a transaction code used for Capac. planning, work center orders in SAP.

SAP CM02 transaction code

It comes under the package CY.When we execute this transaction code, SAPMC65A is the normal standard SAP program that is being executed in background.

SAP CM02 menu path

See the possible menu paths to access the same report by avoiding entering the transaction code.
Path 1
Logistics → Production → Shop Floor Control → Information System → Capacity Evaluation → Work Center View → Orders


Path 2
Logistics → Production → Capacity Planning → Evaluation → Work Center View → Orders


Path 3
Logistics → Production → Capacity Planning → Requirements → Maintenance Order → Capacity Requirements Planning → Evaluation → Work Center View → Orders


Path 4
Logistics → Production – Process → Process Order → Environment → Process Planning → Evaluation → Resource view → Process order


Path 5
Logistics → Production – Process → Process Planning → Evaluation → Resource view → Process order


Path 6
Logistics → Production – Process → Process Management → Environment → Process Planning → Evaluation → Resource view → Process order


Path 7
Logistics → Plant Maintenance → Maintenance Processing → Capacity Requirements Planning → Evaluation → Work Center View → Orders


Path 8
Logistics → Plant Maintenance → Maintenance Processing → Capacity Requirements Planning → Leveling → General → Evaluation → Work Center View → Orders


Path 9
Logistics → Customer Service → Service Processing → Order → Capacity Planning → Evaluation → Orders


Path 10
Logistics → Customer Service → Service Processing → Order → Capacity Planning → Leveling → General → Evaluation → Work Center View → Orders


Path 11
Logistics → Project System → Resources → Capacity Requirements Planning → Evaluation → Work Center View → Orders


Path 12
Logistics → Project System → Resources → Capacity Requirements Planning → Requirements → Maintenance Order → Capacity Requirements Planning → Evaluation → Work Center View → Orders


Path 13
Accounting → Project System → Resources → Capacity Requirements Planning → Evaluation → Work Center View → Orders


Path 14
Accounting → Project System → Resources → Capacity Requirements Planning → Requirements → Maintenance Order → Capacity Requirements Planning → Evaluation → Work Center View → Orders


Path 15
Information Systems → Logistics → Production → Work center → Orders


Path 16
Information Systems → General Report Selection → Production Planning → Capacity Requirements Planning → Capacity Planning, Work Center Orders


Path 17
Information Systems → General Report Selection → Production Planning → Production Control → Capacity Evaluation → Work Center View → Orders


Transaction CM02 technical data table

TcodeCM02
PurposeCapac. planning, work center orders
ModulePP
ComponentPP-CRP
SAP PackageCY
Program runningSAPMC65A
Screen No1
TypeP

Some Basic Questions & Answers

Which SAP Program will run when we enter tcode CM02?
Program named SAPMC65A will run when we enter transaction code CM02.
What is the transaction code type of CM02?
CM02 is a Parameter Transation code type which is shortly represented as P.